Right of Way

FileUpdatedFormatDownload
SLPEMG Rights of Way PDF
Public Access Routes PDF

Local Access Routes

FileUpdatedFormatDownload
Local Access to Kegworth PDF
Local Access to Lockington PDF

Phasing and Programme

Plans of what works will be undertaken at any particular time during the construction period.

Construction programmes are subject to change due to various factors such as weather and unforeseen circumstances so the plans will be updated regularly to reflect actual progress. Please review as may be appropriate for your needs.

FileUpdatedFormatDownload
Public Site Phasing - Plan PDF
Public Site Phasing - Timeline 3
April 2018 to September 2018
 PDF
Public Site Phasing - Timeline 4
October 2018 to April 2019
 PDF
Public Site Phasing - Timeline 5
May 2019 to July 2019
 PDF
Public Site Phasing - Timeline 6
July 2019 to December 2019
 PDF

Kegworth Bypass

We are pleased to announce that work on Kegworth Bypass commenced on 4th September 2017 and is now due for completion early November 2018.

The works are being undertaken by Buckingham Group Contracting limited, who’s contact details are;

Website: www.buckinghamgroup.co.uk

Site email: kegworthbypass@buckinghamgroup.co.uk

FileUpdatedFormatDownload
Kegworth Bypass Summary Works ProgrammeMarch 2018PDF
Proposed public rights of way diversion routesMarch 2018PDF